6MW Solar Project is an Independent Power Purchase Agreement between Tonga Power and Sunergise Ltd, to produce power and sell back on an agreed buying rate per unit by TPL. This IPP Agreement is a 25 yrs deal. There is no battery storage setup attached to this project. It is only rely on its day to day generation and injected to Tonga Power grid.
The project then is divided into three project sites which all locates on the Western District of Tongatapu Island.
Each site will have an estimated install capacity of 2.3MW.
Location of Project Sites
Our Project
We are currently in the implementation phase of upgrading our network to a more safe, reliable and resilient network for our people.
Name of Solar Farm Site | Status of the Project | Challenges |
Fualu Solar Farm – Power Unit 1 | - Vegetation Clearance completed - Fencing with chainlink completed No new activities yet |
COVID-19 impacts on the construction which has cause the international boarder close for many months now.
• Delaying of some of the equipment and materials ETA in Tonga |
Masilamea Solar Farm – Power Unit 2 | - Vegetation Clearance completed - Fencing with chainlink completed No new activities yet |
|
Liukava Solar Farm – Power Unit 3 | - Vegetation Clearance completed - Fencing with chainlink is almost completed No new activities yet |
Below is the projected timeframe each solar power unit site with their commercial operation estimated date. This will be the timeline when each power unit site starts selling their power units generates each day to TPL.